The Steamship Authority last week laid out the work that has been done on the new reservation system and the path forward after the state inspector general raised concerns about the progress toward getting the new booking program online.
Inspector general Jeffrey Shapiro wrote to the ferry line in October and asked for updates and cost breakdowns on the new system, which was delayed due to struggles with the several different ticket options at the Steamship.
In a Nov. 10 letter, Steamship general manager Alex Kryska responded to Mr. Shapiro’s worries by writing that the ferry line has spent $1.6 million of the $2.4 million budgeted to implement the new system, which is being built by E-Dea, an Italian firm with experience with ferries.
About $3.3 million of the total $5.7 million contract with E-Dea is software licensing and hosting for the system through 2030, Mr. Kryska added.
The total implementation cost for the new system, which includes staff training, work to integrate the new system into the rest of the Steamship information technology, and hardware such as ticket scanners, is expected to cost a total of $11.2 million, inclusive of E-Dea’s contract.
According to Mr. Kryska’s letter, only two items have exceeded their initial estimates so far: the bulk shipping portal and network equipment. The former is expected to be $858,555, about $126,000 more than initially budgeted, and the latter is $650,000, or $190,000 over budget.
Mr. Shapiro’s concerns about the reservation system came after he penned a highly critical report on the Steamship’s plans for a new website in 2025. That project was met with several cost overruns and delays; Steamship officials later decided to pause that project to focus on the reservation system.
In that prior report, Mr. Shapiro took the ferry line management to task for not keeping the ferry line board informed on the project. He also felt the board was not asking enough questions of management.
Mr. Kryska highlighted the work that the Steamship has done in the wake of the website report to avoid similar situations.
The Steamship has formed several subcommittees to provide more oversight, and several officials have taken classes with the inspector general’s office.
The overruns on the reservation system have also been relayed to the board, and the updates are provided regularly at the ferry line’s public meetings, Mr. Kryska wrote.
E-Dea is scheduled to deliver a booking system for the high-speed Nantucket ferry next month. Testing would then go through January and it would go live on Feb. 23. The ferry line is looking to roll the system out on the fast ferry first, due to the simplicity of passenger-only tickets.
Public vehicle bookings on the new system are projected to start in July 2027, and terminal scanning by November 2027, according to Mr. Kryska’s letter.
In recent public meetings, Mr. Kryska has expressed frustration about the delays and raised the potential for an outside assessment of the work being done.
Several factors have led to the delays, the general manager wrote in his letter to the inspector general.
Many of the Steamship’s reservation policies were either not written down or inconsistent, prompting the ferry line to start a formalization process. There are also several ticket programs, such as Headstart, excursion, bulk freight, the blue line and standby on Nantucket, that are unique to the Steamship Authority.
A wide range of existing data, such as coupon books, open tickets and gift card balances, also needs to be ported over to the new system, the ferry terminals will need network, cabling and Wi-Fi upgrades, and there also has to be enough time to train staff, Mr. Kryska wrote.
E-Dea has also been late or required fixes along the way, Mr. Kryska added.
“The IT Executive Steering Committee continues to review the project to determine the best course forward,” he wrote. “A responsible schedule must come out of that review rather than precede it, and we will continue to report the project timeline at our public meetings.”
While the new system is being worked on, the existing one continues to handle all reservations and will be online when the Steamship opens the highly-coveted summer bookings for 2027.
Mr. Kryska noted that the previously shelved website, which drew so much scrutiny from the inspector general, will be critical to the new reservation system.
“We cannot overstate this: the protracted monetary investment in the website redevelopment project, while subject to the deficiencies your office found, was not for naught – the website that was built in that project is functional, and is already integrating with the new reservation system,” he wrote.
Mr. Kryska’s letter also walked through several other questions raised by the inspector general, including project management policies and the need to have someone dedicated to overseeing larger efforts.
The inspector general was worried that senior staff, such as the treasurer and chief operations officer, were spending so much time on the reservation system, despite having other duties.
Mr. Kryska agreed with the point and noted that the Steamship was working to create an internal project management office led by a certified project manager. Recruiting for the role is going on now.
“Once the Project Manager is on staff, the Authority will have its own capacity to manage this and future projects, and senior staff involvement will be limited to decisions and approvals within their responsibilities,” Mr. Kryska wrote.
The Steamship Authority welcomed the chance to meet with inspector general and Mr. Kryska wrote that there will be public community meetings over the next week. One on the Vineyard is scheduled for Tuesday at 5 p.m. at the Hebrew Center in Vineyard Haven.
“The [office of the inspector general’s website] report has been a useful roadmap for the Authority,” Mr. Kryska wrote at the end of his nine-page letter. “We remain committed to the accountability and transparency that the public expects of us. Thank you again for your work and for your engagement on these important matters.”
This article appears in November 20 2026.

At the latest IT meeting, Mr. Kryska estimated an additional $815,000 for “Res System Recovery” and an additional $900,000 for “WIFI” — are both amounts included in the $11.2 million total?
The only thing being raised….is are rates!!!!!!!
Am I understanding this correctly? The SSA plans to introduce a new reservation system to the public in July, the middle of the busiest time of the year?
The busiest time of the year for the reservation system is Mid-January to early Feb when the system opens up for summer reservations. Introducing a new system in July is actually a rare intelligent idea from the Steamship.