Alex Kryska started his new role as general manager this month. - Jeanna Shepard

The Steamship Authority’s new general manager, Alex Kryska, began his job last week by tackling last month’s lacerating report by the state inspector general, which called out the authority and previous general manager Robert Davis for wasting millions of dollars on a misconceived website project.

At his first meeting with the Steamship board of governors Tuesday, Mr. Kryska read his draft response to the 59-page report from inspector general Jeffrey Shapiro’s office, saying he wanted to take on these deep-rooted issues.

“I am reviewing it with the board and the Steamship team, and view it as an important tool that will help us strengthen the Steamship Authority’s governance operations and public trust,” Mr. Kryska read.

Many of Mr. Shapiro’s findings — which included the lack of forward-thinking management at the SSA — echo concerns raised in 2018 in a comprehensive third-party review known as the HMS report, Mr. Kryska’s draft letter continued.

“These challenges are longstanding and require focused, sustained action. I’m committed to addressing these issues promptly, transparently and with accountability,” he read from the letter, which went on to outline how he plans to follow up with the board and Steamship staff by using the two reports together as a road map for improvement.

“My focus will be, partnering with the board and port council, on turning these findings into concrete actions, measurable results and lasting change,” Mr. Kryska read.

“By strengthening governance, improving financial discipline and aligning strategy with operations, all coupled with clear and transparent communications, the Steamship Authority can better fulfill its mission to the islands and the traveling public,” the letter concluded.

The board of governors will review Mr. Kryska’s draft response and discuss his action plan in depth at their next meeting in February, board chair Peter Jeffrey said.

Mr. Kryska, a former ferry executive in the San Francisco Bay area, was hired in November after an international search for a successor to Mr. Davis, who has moved to an advisory position reporting to the board.

Now in his second week on the job, Mr. Kryska told the board he has met much of the Steamship Authority staff, which numbers more than 750 in high season.

“I’ve been very pleased with how hard working and diligent they are,” he said.

Mr. Kryska also was on hand when the authority’s newest freight ferry, M/V Monomoy, arrived Monday morning at the Steamship maintenance facility in Fairhaven.

“It was very exciting to see the boat roll in [and] to see all the families there, and the crew,” he said.

The Monomoy — sister ship to M/V Aquinnah and M/V Barnstable, all converted from oil field support vessels to freight and passenger ferries — left the Mobile, Ala. shipyard the afternoon of Jan. 7 and holed up in Morehead City, N.C. during some foul weather, director of engineering and maintenance Zach Lawrence said.

To avoid winter sea weather in the Northeast, Mr. Kryska said, the Monomoy took the inside passage through New York City and Long Island Sound on its way to Fairhaven.

The ferry still has some equipment to be installed, such as Wi-fi and vending machines, and must receive its local Coast Guard certifications before entering Steamship service, Mr. Lawrence said.

The Steamship Authority has expended about $86 million of a projected $87.3 million to purchase, convert and equip the three boats, Mr. Lawrence said.

In 2022, when the first two purchases were authorized, Mr. Davis estimated the combined cost of buying and converting the vessels at about $16 million each, or $48 million.

Vineyard board member James Malkin, who is not seeking another term when his current three-year appointment ends in March, said that despite cost overruns, the acquisition was a good move. 

“When the board took the decision to go after these three vessels, we did so because we’d have identical vessels, identical training with identical crewing and identical capacity, which is very important when we swap vessels,” Mr. Malkin said.

“I think the three vessels that we now have are a terrific investment in the Steamship Authority,” he said.

“A new … hybrid [passenger ferry] would probably cost us $100 million,” Mr. Malkin said.

In other business Thursday, the board of governors reluctantly approved — with Moira Tierney dissenting outright — a change order reflecting a 50 per cent increase in the budget for dock work at the Vineyard Haven terminal, raising the cost by more than $400,000.

Cracked concrete beneath the dock’s surface is proving to be more extensive than previously known, chief operating officer Mark Amundsen said, raising repair costs far beyond the budget’s original 25 per cent contingency.

“It’s not possible to put a firm amount of [repair] area in this contract [because] we don’t know the full scope until we excavate the property,” Mr. Amundsen said.

Overall, the Vineyard Haven terminal is in good shape, he said.

“We’ve done all the underwater [surveys] on all the pilings, and they’re in excellent condition,” Mr. Amundsen said.

Ms. Tierney questioned how the 25 per cent contingency — an agreed-upon cap on extra spending caused by unexpected discoveries — could have fallen so far short of the reality.

“This doesn’t seem well thought out at all,” she said. “When you’re dealing with cement, I would think that that would be foreseeable.”

As explained by Mr. Lawrence, a flaw in the request for proposals from contractors led to a winning bid that was based on areas of the dock that were known to be defective, rather than on the total area where repairs would be conducted.

To prevent similar problems in the future, the engineering and maintenance department now is employing both a clerk of the works and an owner’s project manager to review requests for proposals before they are issued, Mr. Lawrence said.